ALEKSEEVSKA Oil Mill – C.I.S., Russia

EFKO

Supply of crushing, refining and fat modification equipment

Customer
JSC EFKO -Alekseevska - Russia
General contractor
iAG Holdings - Engineers & Contractors
Scope of works
Design, supply, supervision of Installation and commissioning
Industrial operation
Extraction: 1997
Refining: 1999
Fractionation: 2002
Main sub-contractors involved
iAG Holdings - Technologies & Services - The Netherlands
Plant capacity
Crushing: 300 MTPD
Refining: 230 MTPD
Fats refining / Fractionation / Hydrogenation / Interesterification: 100 MTPD

Processing units :
- Oil refining plant complete with physical /
- chemical refinery unit,
- bleaching unit, winterising unit and deodorising unit
- Hydrogenation & post treatment unit
- Interesterification unit
- Deodorizing unit
- Double dry fractionation unit
- Tank farms
Utilities :
- Hydrogen production unit
- Nitrogen production unit
- Laboratory pilot unit
- Tank farms